Does anyone have information on the well drilled by Wildhorse/Chesapeak in the Nixon Lake Unit?

Thanks, R.J. Harbaugh

Only information I can find on that well is that they finished drilling it in Mid-March. I would expect it to be fracked and online very soon.

This weekend big completion wellheads were installed on all three wells Chesapeake drilled from that pad and frack equipment is moving in. The new pipeline is in the ground from the pad out to Oevermann Road and the tie-in to Energy Transfer’s gathering system is underway.

Completing fracks on all three wells will take several weeks. After that, if Chesapeake follows the same pattern Wildhorse did, completion reports for the Nixon Lake unit and other two units probably won’t be filed for months and it could be September or later before first “pending” production reports show up on RRC.

Thanks for the info

RJH

Thanks, good info and seems to be good news.

Regards, RJH