We have a non-op WI in 12 gas wells that are all waiting for flow meters from the utility company. We are now over 6 months on the wait list with no scheduled hook-up in sight. Has anyone experienced a similar situation and what could be a possible work around. Unfortunately, our operator is not a large operator. Thank you for any guidance. Rob
1 Like
Read your lease to see what your shut-in payments could be. They do not usually kick in until one year after completion. Have you contacted the operator to see what their plans are?