Is there any information on theses drilling activities?
Ceth,
The only thing that I find at this time is that Sawyer 1H was spud (begin drilling) on May 3, 2017. I do find an approved permit for Sawyer 1 but no spud date.
Clint Liles
Thank You Clint!
I noticed that they had a may spud date, but haven't seen any production
I noticed where Sawyer !H was completed. Is there anywhere that predicts well potential?
Ceth,
the numbers on the Completion Report for Sawyer 576 1H are not good for a Horizontal well. 57 barrel oil per day/45,000 cubic feet gas per day...
Clint Liles
Thanks Clint!
Sawyer 576
6 results Page: 1 of 1 Page Size: Date OIL (BBL) Casinghead (MCF) Operator Name Operator No. Field Name Field No. Production Disposition Production Disposition Aug 2017 570 354 556 556 WALSH PETROLEUM, INC. 894720 BRAHANEY 11308001 Sep 2017 2,399 2,266 1,761 1,761 Oct 2017 4,762 4,720 3,444 3,444 Nov 2017 NO RPT NO RPT NO RPT NO RPT Dec 2017 NO RPT NO RPT NO RPT NO RPT Jan 2018 NO RPT NO RPT NO RPT NO RPT Total 7,731 7,340 5,761 5,761
David,
Does this well have any new reports?
We just got a production report for our share and it showed gross 70,000 from August to May